BUILDING PROCESS
This process is based on a two story residential home.
CHOOSE A STAND
Who came first – chicken or the egg? builder or the architect? We say the informed customer came first! Buying a stand is all about $, size, layout (North East South West facing?), servitudes, estates rules & architectural guidelines – your builder & architect needs to know their stuff.
WHICH ARCHITECT?
How much will he charge for MY idea? single or double storey? Plastered walls or Facebrick, Wood or Aluminium doors & windows? How do I minimise Yearly & Monthly Maintenance? Green Footprint -solar geyser? gas geyser? heatpump? gas stove? Grey water system? Insulation? Cavity walls? Double glazing windows? Underfloor heating or Gas Fireplace? How many bedrooms & ladies how much cupboard space is enough?, bathroom layout & sanitary ware that saves water? Living & Entertainment? Bar? Study? Garage & Storage? Servants quarters? Future possibilities for extension like a extra room or swimming pool? Where is what light installed and what light switches goes where? How high is my shower head and how wide is my bath – will it fit practically like the architect indicated? Cornice mould? Skirting size? Type of Floor & Wall tile? Bedrooms – carpets or laminates? Kitchen planning & layout? wall color choices? #&%$ this is too much!!
But wait we can help…we help with the design & its included in our price! That’s not all we also assist with…
INTERIOR PLANNING
We supply a mood board to help visualize the final product vs. budget.
BUILDER QUOTATION
All the above questions affects Rand per m2 – Builders tender & documents (contract)
BANK DOCUMENTS
All banks need different documentation but most want a Bank Agreement, Tender & Contract with a Builder, Waiver of Lien, NHBRC Enrollment & Registration, Interest letter, etc.
APPROVAL FROM BANK
All banks need different documentation but most want a Bank Agreement, Tender & Contract with a Builder, Waiver of Lien, NHBRC Enrollment & Registration, Interest letter, etc.
ATTORNEY INSTRUCTION
Client signs all documentation with the attorney.
HOME OWNERS ASSOCIATION APPROVAL
We supply a mood board to help visualize the final product vs. budget.
COUNCIL APPROVAL
All the above questions affects Rand per m2 – Builders tender & documents (contract)
NHBRC SUBMISSION
Depending on the soil conditions, area & NHBRC engineers.
Tshwane 4-6 Weeks
Ekurhuleni 6-8 Weeks
Jo’burg up to 12 Weeks
ATTORNEY REGISTERS STAND AND BUILDING BOND
All banks need different documentation but most want a Bank Agreement, Tender & Contract with a Builder, Waiver of Lien, NHBRC Enrollment & Registration, Interest letter, etc.
Once all the above ducks are in a row we GO GO GO…
OK, now we start:
PROJECT PLANNING
WHEN must we order WHAT to fit the budget
HOME OWNERS ASSOCIATION
Approves site establishment
SITE ESTABLISHMENT
We clear the site of all rubble & grass, Land surveyor for stand beacons and house points, Temporary power & Toilet facilities, Water Connection & storage facilities
HOME OWNERS ASSOCIATION APPROVAL
2 days
Excavate trenches, sewer & boundary wall
1 day
Engineer Council HOA & Bank inspect trenches
3 days
Engineer designs foundation – steel ordered
1 week
Compaction of trenches & fixing of steel
1 day
Concrete in foundations
Progress payment – The first one can take up to 3 weeks
BUILDING FOUNDATION WALLS
1 week
Backfill & level inside of foundation walls to prepare for surface bed steel & concrete Once leveled plastic is installed for waterproofing & welded mesh for surface bed strength.
2 weeks
Installation of electrical conduit for plugs & light switches & plumbing wastes for bath shower & basins.
1 day
Pouring of concrete for the surface bed.
BUILDING GROUND FLOOR WALLS
Building of ground floor external and internal walls, including lintels and brick force. To prepare for 1st floor slab.
SLAP PREPARATION
Preparing for the 1st floor slab.
BUILDING FIRST FLOOR WALLS
Building of first floor external and internal walls, including lintels and brick force. To prepare for roof installation.
ROOF
1-2 days : Erect Trusses & Insulation
1-2 days : Install roof tiles
BUILDERS TO FINISH
Building Internal Door Frames, Beam filling, Gables, Window Sills, Braai, Fireplace, Boundary & Screen Walls.
CLIENT INSPECTS
Planned Plumbing & Electrical points before plaster.
Plumber & Electrician installs Geyser & Main Power supply, conduit, pvc pipes & copper into Ground floor & First Floor walls.
INSTALLING
Wooden or Aluminum Windows + Garage Door – Prepare for installation of outside doors to lock the house.
PLASTER
Team starts inside with the walls & Floor screed
CEILINGS
Ceilings are now installed – Rhinolite on the ceiling starts in the first finished room
PAINTERS ARRIVE
Painter starts with waterproofing & the BEST primer money can buy (off course this is included).
Client chooses final sample colour for inside, outside and a matching tile.
TILES ARRIVE
INTERNAL DOORS
PLASTER TIME
KITCHEN
CEILING GUY
PAINTER
ELECTRICAL
BATHROOM
PAINTER
ELECTRICAL
Final Electrical, Stove & Light fittings installed.
BATHROOM
Final bathroom fittings installed.
STAIRCASE BALUSTRADES & GARDEN GATES
SHOWERS, MIRRORS AND BATHROOM ACCESSORIES
PREPARE FOR IRRIGATION BEFORE PAVING
CLEARING
FLOORING
INSPECTION
CLEANERS
COMPLETION